Main Street-Phase One

Project Purpose: Improve the aesthetic of the street in order to attract shoppers, tourists, and reinvestment in the buildings
Project Area: Main Street from  Wayne Avenue to Arch Avenue
Types of Physical Improvements: New sidewalks, bricked bump outs, street lights,  and repaving of Main Street.
Budget:
Grant/ Fundraising Period: 2000 to 2005
Funding Source: Federal Transportation Enhancement Grant/ 20% City Match
Construction Period: 2006
Current Status:  Completed 2006
Contact Person: Michael Barnes, Director of Planning (540) 942-6604